For a covered non-domestic private rented property in England or Wales, the current Minimum Energy Efficiency Standard (MEES) is generally EPC band E. A landlord must not grant a new tenancy, renew or extend an existing tenancy, or continue letting a sub-standard property unless the property reaches EPC E or a valid exemption has been registered. Holding an EPC is not the same as passing MEES: an F or G certificate can be valid as a document while the letting remains restricted.

The practical pre-letting question is therefore two-part: does the premises need a commercial EPC, and if it does, does the letting comply with MEES? The answer depends on the building, the tenancy, the EPC rating, the timing of the transaction and any registered exemption. This guide explains the checks for offices, shops, industrial units and other non-domestic premises without treating a general EPC article as a substitute for commercial MEES analysis.

EPC And MEES Are Related But Different

An Energy Performance Certificate rates a building from A, the most efficient band, to G, the least efficient. It is produced following an assessment by an accredited energy assessor and includes information about the building’s energy performance and possible improvements. GOV.UK states that commercial EPCs are valid for 10 years, although a newer certificate can replace the earlier one. 

MEES is the letting restriction layered on top. It uses the EPC rating to set a minimum efficiency level for relevant privately rented non-domestic property. A certificate answers “what rating was assessed?” MEES answers “may this landlord let or continue letting this property in these circumstances?” Keeping those questions separate prevents a common error: assuming that an in-date EPC automatically gives permission to let.

The Current Commercial Position At A Glance

Question

Practical answer

Evidence to retain

Minimum rating

Generally EPC E for covered non-domestic private rented property

Current EPC and MEES review

Certificate validity

Usually 10 years, unless a newer EPC is produced

EPC reference and issue date

F or G rating

Do not let or continue letting unless the property is outside scope or a valid exemption is registered

Scope analysis or exemption record

Exemption evidence

Depends on the exemption; commercial seven-year payback evidence may include three installer quotes and calculations

PRS Exemptions Register record and supporting documents

Which Commercial Properties And Tenancies Are Covered?

The non-domestic MEES Regulations apply to privately rented non-domestic properties that are legally required to have an EPC and are let on a relevant tenancy type. The official landlord guidance gives examples of exclusions, including a term certain of six months or less in specified circumstances and a term of 99 years or more. It also asks whether the property is non-domestic, whether it needs an EPC and whether the tenancy falls within the relevant duration range. 

Do not decide scope from the property label alone. A “shop”, “warehouse” or “office” can have different EPC and letting circumstances. A building may also contain separate units, mixed uses or services that affect the assessment. Confirm the premises being let, the lease term, whether the accommodation is separately occupied and whether an EPC is legally required for that particular transaction.

When Did The MEES Restrictions Apply?

Since 1 April 2018, landlords of covered non-domestic property have generally needed at least EPC E to grant a new tenancy or renew or extend an existing tenancy, unless a valid exemption applied. Since 1 April 2023, the requirement has applied to all privately rented non-domestic property within scope, even where there has been no change in tenancy. 

That does not mean every empty building automatically needs immediate improvement. The guidance explains that if a property is empty and the owner is not planning to let it, action to improve the rating is not required until the owner decides to let it again. Pre-letting work should still begin early because commissioning an EPC, obtaining quotes, securing consent and registering an exemption can take longer than the marketing timetable.

What To Check Before Marketing Or Granting A Lease

A commercial landlord should complete the following sequence before treating a unit as ready to let:

  • Identify the exact space and tenancy to be granted, including any mixed-use or multi-let arrangement.

  • Check the government EPC register or property file for the latest certificate, rating, issue date and building reference.

  • Confirm that the certificate describes the accommodation being marketed and has not been superseded by a newer EPC.

  • If the rating is E or better, record the MEES check and review any lease, lender or investor requirements that go beyond the statutory minimum.

  • If the rating is F or G, establish whether improvements can bring the property to E and whether consent, funding, fabric or payback issues affect the plan.

  • If an exemption may apply, gather the required evidence and register it before relying on it.

  • Give the agent and transaction team a clear status: compliant, improvement programme, or registered exemption with expiry date.

The point of this workflow is to expose the “almost ready” property. An EPC that expired last month, a certificate for the wrong unit, or an exemption that was never registered can create a delay after marketing has already started.

Can You Let A Commercial Property With An EPC Rating Of F Or G?

Usually not if the property and tenancy are covered by the non-domestic MEES Regulations. An F or G rating is not automatically unlawful in every circumstance: the property may be outside scope, or a valid exemption may apply. But the landlord should not assume that an old certificate, a planned refurbishment or an informal agreement with the tenant is enough.

Office Example

An office has an EPC rating of F and the owner wants to grant a five-year lease. The landlord should first review the EPC recommendations and obtain realistic installation costs. If relevant improvements can bring the building to E, the owner should plan that work. If the package fails the commercial seven-year payback test or another exemption applies, the owner must collect the prescribed evidence and register the exemption before relying on it.

Retail Example

A shop has an EPC E, but the certificate describes the whole building while the proposed letting covers a separately occupied unit created after alterations. The landlord should confirm that the EPC remains appropriate for the accommodation being let. A rating on a certificate for a different configuration is not a reliable substitute for the correct assessment.

Industrial Example

A lightly serviced industrial unit has an F rating and the landlord believes it uses little energy. That fact alone does not prove that the property is exempt from EPC or MEES rules. The owner should check the official categories and the actual tenancy circumstances, then document the conclusion.

Commercial MEES Exemptions And Evidence

An exemption is not a general permission to let a poor-performing property. It is a specific route with eligibility conditions, evidence and registration. The PRS Exemptions Register guidance states that an exemption must be registered before it can be relied on, and that the registration is generally made by self-certification with supporting information. 

The Seven-Year Payback Test

For non-domestic property, a recommended measure or package can fail the seven-year payback test when the expected value of energy-bill savings over seven years is less than the cost of purchasing and installing it. The evidence guidance says commercial landlords should upload three quotes from qualified installers, confirmation that the test is not met and the cost calculations. This exemption lasts five years before the landlord must try again or register another valid route. 

Do not use the £3,500 high-cost exemption as a commercial shortcut. The official guidance identifies that cost-cap exemption as domestic-only. Non-domestic landlords should assess the seven-year payback framework and the other commercial exemptions instead.

Other Routes That May Apply

  • All improvements made: relevant improvements have been completed, or none can be made, but the property remains below E.

  • Wall insulation: expert evidence shows that specified wall insulation would negatively affect the fabric or structure.

  • Third-party consent: required consent, such as planning, lender, superior landlord or tenant consent, cannot be obtained or carries conditions that cannot reasonably be met.

  • Property devaluation: evidence shows that carrying out the improvements would reduce the property’s value by more than the threshold set in the regulations.

  • Temporary exemption: limited circumstances apply when a person has recently become a landlord.

Each route has different evidence and duration rules. Save the EPC, quotes, calculations, expert opinions, correspondence and registration details together. An exemption may not transfer automatically when a property changes ownership, so a purchaser who intends to continue letting should check the position afresh.

Commercial EPC Validity And Portfolio Records

A commercial EPC is generally valid for 10 years, but a newer EPC for the same building can replace it. An owner should track the certificate reference, issue date, expiry window, rating, property configuration and any improvement works completed since assessment. A certificate that is technically in date may still be a poor management record if it does not reflect a major refurbishment, subdivision or change in services.

For a portfolio, keep a schedule with separate columns for EPC status and MEES status. This distinction is useful because “EPC available” is not the same as “letting permitted”. Add exemption type, registration date, expiry or review date, responsible person and the next action. Make the record accessible to the landlord, managing agent and transaction team.

Enforcement Risks And Compliance Notices

Non-domestic MEES is enforced by local weights and measures authorities. GOV.UK explains that an authority may issue a compliance notice requesting information, including the EPC valid when the property was let, the tenancy agreement, improvement details and other relevant documents. A breach or false or misleading exemption information can lead to financial penalties. 

Good records do not replace compliance, but they make the landlord’s position clearer. Keep the version of the EPC used for the transaction, copies of notices and marketing instructions, improvement evidence, exemption registration and communications with agents or tenants. If an authority asks questions, a complete file is more useful than a statement that “the property had an EPC”.

How Global Compliance Can Help With EPC Planning

Global Compliance provides EPC assessments for residential and commercial properties, with accredited assessors, site visits, fast turnaround and recommendations that help owners understand practical efficiency improvements. The EPC service page describes assessments that consider the building’s performance and outline measures involving insulation, heating and lighting.Explore the commercial and residential EPC service for scope and booking information.

An EPC assessment is the starting point, not the whole MEES decision. If the result is F or G, the landlord should use the certificate with commercial cost evidence, consent information and legal guidance to decide whether to improve, register an exemption or confirm that the property is outside scope. Global Compliance’s existing EPC explainers provide additional background on ratings, recommendations and property-market considerations.What EPCs are and why they matter | How EPCs impact property value and rental.Contact Global Compliance to arrange an assessment or discuss a commercial property portfolio.

Frequently Asked Questions

What is the minimum EPC rating for commercial property?

For covered non-domestic private rented property in England and Wales, the current MEES minimum is generally EPC band E, unless the property is outside scope or a valid exemption has been registered.

Does every commercial property need an EPC?

Many commercial premises need an EPC when sold or rented, but exemptions and special categories exist. GOV.UK lists examples such as certain listed or protected buildings, temporary buildings, places of worship, low-energy industrial or agricultural buildings, small detached buildings and buildings due for demolition, subject to the stated conditions.

Is the commercial MEES exemption cost cap £3,500?

No. The £3,500 high-cost exemption is identified in the official evidence guidance as domestic-only. Non-domestic landlords should consider the seven-year payback test and other applicable exemptions.

How long is a commercial EPC valid?

Usually 10 years, unless a newer EPC is produced for the building. Always check that the certificate matches the premises and configuration being let.

Can an exemption be transferred to a buyer?

Do not assume so. The official exemptions guidance warns that a registered exemption may cease to be effective when the property is sold or transferred, requiring the new owner to improve the property or register an exemption if they intend to continue letting it.


 
 
 